Highways
Approval of all traffic management requests are sought from our Highways Department and permission is granted on a case by case basis.
TRAFFIC MANAGEMENT REQUEST | COST | LEAD TIME | ADMIN FEE |
Traffic management order (TMO) | £500 | 5 working days | £175 |
Road closure by notice | £1750 | As necessary / by agreement | £175 |
Road closure by order | POA | 4 – 6 weeks | £175 |
Crane licence | £250 | 7 days | £150 |
Street furniture alterations | POA | 7 days | £150 |
Lighting engineer | POA | 7 days | £150 |
- For all traffic management requests, you will need provide us with:
- A traffic management plan (TMP), which clearly illustrates/maps out the area you are intending to use with operative station and signage points
- Risk assessment and method statement
- The TM company instructed by the production will need to full accredited and evidence of this will need to be provided